About the Project:
This project was your typical scenario with a row of terrace homes in paddington where all the houses were connected to the shared sewer line before it reached the Sydney Water Main.
The Problem:
Tree roots were entering the defected collars along the complete pipe causing blockages. As there were multiple houses connected into to this drain we required to split the quotation amongst all 5 owners as it was a shared service so they shared the cost.
How We Fixed It:
Using our Brawoliner Inversion lining method we relined over 30m from the furthest house at the end of the line down to the boundary trap to seal the pipe with one continuous liner. Once the liner had cured we robotically reinstated all the branch line junctions that connected into this drain.